Join any timeJob or full-time? One course for bothMains Answer Writing: every copy checked by Amit SirNew: Prelims PYQ Book ₹199Free: 500 Prelims PYQs with explanationsSee a real Mains copy checked by Amit SirJob + APSC? Evening classes, 7 to 9 PMEvery class recorded, rewatch anytimePrelims + Mains + Interview, one coursePrelims only? Crash Course from ₹2,499JE, AE, ADO? The GS paper is common: see howJoin now

APSC Answer Writing (Daily) based on Assam Tribune – 25/11/2026

By Amit BiswakarmaPublished 3 min read
This question comes from today’s Assam Tribune notes:Full Assam Tribune notes →Only today’s MCQs →

For APSC CCE and other Assam Competitive examinations aspirants, practicing Daily Answer Writing is vital. This blog covers the most important Main question and its model Answer from the Assam Tribune today (25-11-2026).

APSC Mains Answer Writing Program 2027Recommended courseAPSC Mains Answer Writing Program 2027₹4,999 ₹8,999 44% offView course

Mains Answer Writing

From The Assam Tribune, 25 November 2026

Mains question · 15 marks · 250 words

Q. Recently, the Demwe Lower Hydroelectric Project on the Lohit river in Arunachal Pradesh has again drawn objections. Discuss the environmental concerns of large hydroelectric projects in the Eastern Himalaya, including their downstream impact on Assam. Also evaluate how far the forest and wildlife clearance process balances hydropower needs with biodiversity protection. (250 words, 15 marks)

Model answer

Introduction: In a letter dated 23 November 2026, 69 former bureaucrats asked the Union Environment Ministry to scrap the 1,750 megawatt (MW) Demwe Lower project on the Lohit. It needs 1,416 hectares of forest and about 43,000 trees felled, in a state with over 50,000 MW of hydropower potential.

1. Environmental concerns of large hydroelectric projects in the Eastern Himalaya

  • Hotspot forests: Arunachal Pradesh lies in both the Himalaya and Indo-Burma biodiversity hotspots. Demwe Lower alone would submerge about 1,590 hectares in a highly sensitive evergreen rainforest.
  • Endangered species: The project threatens the white-bellied heron, which the International Union for Conservation of Nature (IUCN) lists as Critically Endangered. Fewer than 250 mature birds survive worldwide.
  • Broken corridors: The dam would split tiger habitat across Kamlang, Namdapha and the proposed Dibang Tiger Reserve.
  • Sacred river at stake: Mishmi and other tribes have resisted the dam since its 2010 environmental clearance. They want to protect the sacred Parashuram Kund.
  • Weak data: In 2018, the Wildlife Institute of India (WII) found the dam’s hydrological modelling coarse, with little data. So flooding of river islands could not be ruled out.

2. Downstream impact on Assam

  • Dibru-Saikhowa at risk: Assam’s Dibru-Saikhowa National Park lies downstream of Demwe Lower. In 2018, the National Board for Wildlife (NBWL) required a study of flood impact on the park.
  • Peaking floods: Water released at peak demand hours raises river levels daily and disturbs the natural seasonal flood cycle. This could flood chaporis (river islands) used by tigers, Bengal floricans and elephants.
  • Dam safety fears: The All Assam Students’ Union (AASU), Krishak Mukti Sangram Samiti (KMSS) and others stalled the 2,000 MW Subansiri Lower project over safety and downstream concerns. Work stopped on 16 December 2011 and resumed only in 2019.
  • Assam left out: The Kameng basin study recommended 37 projects of 2,561.9 MW. Critics said it ignored Assam’s Nameri National Park, and no official public consultation was held in Assam.

3. How far the forest and wildlife clearance process balances hydropower needs with biodiversity protection

Strengths of the processGaps seen in practice
The Van (Sanrakshan Evam Samvardhan) Adhiniyam, 1980 needs prior Central approval before forest land is diverted.Demwe got wildlife clearance in 2012, though all non-official experts on the Standing Committee had rejected it in October 2011.
The NBWL Standing Committee exercises the Board’s powers under Section 5B of the Wild Life (Protection) Act, 1972.The Union Environment Minister chairs the Committee, so official views can override the experts.
Hydroelectric projects of 50 MW and above need central Environmental Impact Assessment (EIA) clearance.Project-wise EIAs miss the combined effect of many dams on one river basin.
The National Green Tribunal (NGT) suspended Demwe’s forest clearance in October 2017.The NGT found that majority expert objections had been set aside without proper reasons.
The NBWL’s 2018 approval barred peaking operations until a two-year study was done.That study runs alongside dam construction, not before it.

Judgement: The process strikes this balance only partly. Its laws and safeguards are strong on paper. But in Demwe, officials overruled experts and let key studies trail construction, so hydropower needs won.

4. Way Forward

  • Basin-first planning: The Environment Ministry should clear projects only after a basin-wide impact study covering Assam’s floodplains.
  • Respect experts: The NBWL Standing Committee should record written reasons whenever it differs from its expert members.
  • Studies before concrete: Peaking and downstream flood studies should finish before construction begins.
  • Voice for Assam: Hold public hearings in downstream Assam districts and consult Assam’s Chief Wildlife Warden.
  • Community rights: Arunachal Pradesh should settle Forest Rights Act, 2006 claims of tribal gram sabhas before any forest diversion.

Conclusion: Demwe Lower shows that Eastern Himalayan hydropower is acceptable only if it does not cost the hotspot forests and Assam’s floodplains. Basin-wide science and local consent must come before approval, not after it.